Alliant Energy is partnering with MJ Electric to convert overhead electric lines to underground along 42nd St NE in Cedar Rapids. This will ensure safe and reliable service to the community.
Following construction in each area, necessary repairs to restore property will be made as efficiently as possible.
affected area | project type | anticipated construction completion date |
anticipated restoration completion date |
---|---|---|---|
42nd Street NE
|
Overhead to underground rebuild | Underground installation has been completed. Some conversion work/ outages to customers will not take place until end of 2024 due to transformer shortages. | Complete |
Alliant Energy is partnering with MJ Electric to convert overhead electric lines to underground in the Cherry Ln NE area of Cedar Rapids. This will ensure safe and reliable service to the community.
Following construction in each area, necessary repairs to restore property will be made as efficiently as possible.
affected area | anticipated start date |
project type | anticipated construction completion date |
anticipated restoration completion date |
---|---|---|---|---|
Wenig Rd, White Pine Dr, Aspen Ln, Marsue Cir, Towne House Dr, Fairlane Dr, Northwood Dr, Marilyn Dr, Cherry Ln, 42nd St, Lorcardo Dr, David Ct
|
November 2023 | Overhead to underground rebuild | Underground installation has been completed. Some conversion work/ outages to customers will not take place until end of 2024 due to transformer shortages. | Complete |
Alliant Energy is replacing and upgrading existing underground electric lines at Granite Valley Apartments on the northeast side of Cedar Rapids. This will ensure safe and reliable service to the Apartments. Following construction, necessary repairs to restore property will be made as efficiently as possible.
affected area | anticipated start date |
project type | anticipated construction completion date |
anticipated restoration completion date |
---|---|---|---|---|
Boyson Rd, Country Hill Ln, Country Hill Ave, Country Hill Ct, Country Hill Cir, Country Hill Rd
|
Summer 2024 | Underground rebuild | December 2024 | August 2024 |
Alliant Energy is replacing and upgrading existing underground electric lines along Lexington Dr NE on the northeast side of Cedar Rapids. This will ensure safe and reliable service to the neighborhood.
Installation of underground facilities will begin in August 2023. Following construction, necessary repairs to restore property will be made as efficiently as possible and are expected to be complete by December 2023.
affected area | anticipated start date |
project type | anticipated construction completion date |
anticipated restoration completion date |
---|---|---|---|---|
Lexington Dr, 42nd St, Blue Jay Dr, Summerfield Ln, Foxborough Ter
|
August 2023 | Underground rebuild | Underground installation has been completed. Some conversion work/ outages to customers will not take place until end of 2024 due to transformer shortages. | Complete |
Alliant Energy is replacing and upgrading existing underground electric lines along Morelle Road NE on the northeast side of Cedar Rapids. This will ensure safe and reliable service to the neighborhood.
This project is on hold due to a nationwide transformer shortage. The project will begin again when transformers become available.
Following construction, necessary repairs to restore property will be made as efficiently as possible.
affected area | anticipated start date |
project type | anticipated construction completion date |
anticipated restoration completion date |
---|---|---|---|---|
Morelle Rd, Woodsmill Dr, Millbrook Ct
|
Summer 2023 | Underground rebuild | Underground installation has been completed. Some conversion work/ outages to customers will not take place until end of 2024 due to transformer shortages. | Complete |
Alliant Energy is partnering with MJ Electric to convert overhead electric lines to underground in the area south of Sally Dr NE, Cedar Rapids. This will ensure safe and reliable service to the community.
Following construction in each area, necessary repairs to restore property will be made as efficiently as possible.
affected area | anticipated start date |
project type | anticipated construction completion date |
anticipated restoration completion date |
---|---|---|---|---|
Falbrook Dr, Glen Elm Dr, 42nd St, Wenig Rd, Falcon Dr, Brookland Dr, Tanager Dr, Amber Dr, Glass Rd
|
July 2023 | Overhead to underground rebuild | Underground installation has been completed. Some conversion work/ outages to customers will not take place until end of 2024 due to transformer shortages. | Complete |
Alliant Energy is replacing and upgrading existing underground electric lines in the Westchester Dr NE area of Cedar Rapids. This will ensure safe and reliable service to the neighborhood.
Installation of underground facilities will begin in April 2023. Following construction, necessary repairs to restore property will be made as efficiently as possible.
affected area | anticipated start date |
project type | anticipated construction completion date |
anticipated restoration completion date |
---|---|---|---|---|
Westchester Dr, Towne House Dr, Coventry Ln, Sugar Pine Dr, Pineview Dr, Twin Pine Dr
|
April 2023 | Underground rebuild | Underground installation has been completed. Some conversion work/ outages to customers will not take place until end of 2024 due to transformer shortages. | Complete |
Alliant Energy is replacing and upgrading existing underground electric lines in the Wolf Creek Trail NE area of Cedar Rapids. This will ensure safe and reliable service to the neighborhood.
Installation of underground facilities will begin in June 2023. Following construction, necessary repairs to restore property will be made as efficiently as possible.
affected area | anticipated start date |
project type | anticipated construction completion date |
anticipated restoration completion date |
---|---|---|---|---|
Falbrook Dr, Glen Elm Dr, 42nd St, Wenig Rd, Falcon Dr, Brookland Dr, Tanager Dr, Amber Dr, Glass Rd
|
July 2024 | Overhead to underground rebuild | Underground portion to be done by October of 2023. Some conversion work/ outages to customers will not take place until 2024 due to transformer shortages. |
December 2024 |