Alliant Energy is replacing and upgrading existing underground electric lines on 31st St SW Cedar Rapids. This will ensure safe and reliable service to the neighborhood. Following construction, necessary repairs to restore property will be made as efficiently as possible.
AREA IMPACTED | anticipated start date |
project type | anticipated construction completion date |
anticipated restoration completion date |
---|---|---|---|---|
31st St, Van Buren Dr, 29th St, 30th St, Hillmer Dr
|
Summer 2024 | Underground rebuild | December 2024 | December 2024 |
Alliant Energy is replacing and upgrading existing underground electric lines at Cedar Valley Townhouses in SW Cedar Rapids. This will ensure safe and reliable service to the townhouses. Following construction, necessary repairs to restore property will be made as efficiently as possible.
area impacted | anticipated start date |
project type | anticipated construction completion date |
anticipated restoration completion date |
---|---|---|---|---|
Cedar Cir, J St
|
Summer 2024 |
Underground rebuild | December 2024 | December 2024 |
Alliant Energy is replacing underground electric lines on the southwest side of Cedar Rapids. This will ensure safe and reliable service to the neighborhood.
Alliant Energy completed underground boring.
This project is on hold due to nationwide transformer shortage. We will begin construction again when transformers become available.
Following construction, necessary repairs to restore property will be made as efficiently as possible. Weather conditions may delay full restoration until the spring. For questions on property restoration, please call 1-800-ALLIANT (800-255-4268) or fill out the Construction Contact Form.
Area Impacted | Anticipated Start date | Project Type | Anticipated CONSTRUCTION COMPLETION DATE |
ANTICIPATED RESTORATION COMPLETION DATE |
---|---|---|---|---|
Cherry Hill Rd SW, Fleetwood Rd SW, and W Post Rd SW
|
June 2022 | Pulling in wire, replacing transformers, connecting underground cables and converting to the new underground system |
Project on hold | TBD |